Lucara Diamond Corp.
investors

president's message


Second Quarter 2010


HIGHLIGHTS

AK6 Diamond Project - Botswana
  • A bankable feasibility study was completed in June 2010.

  • Phase I will require an estimated capital investment of US$120 million, including contingency, for the design and construction of a production facility with an initial throughput of 2.5 million tonnes per annum. Average operating costs over the life of mine are estimated to be US$17.51 per tonne treated.

  • Project engineering was awarded to DRA African (Pty) Ltd.

  • Amendments to diamond sales provisions of the mining licenses were formally approved by the Government of the Republic of Botswana.
Mothae Diamond Project - Lesotho
  • Planned upgrades to the bulk sample plant were completed.

  • Test trial mining operations commenced in late May.

  • A 53.3 carat, Type lla diamond was recovered in the first week of processing.

  • Plant commissioning is underway with the process feed expected to ramp up to design capacity of 30,000 per tonnes per month.

First Quarter 2010


Annual Report (For the Five Month Period Ended Dec. 31, 2009)


2010 First Quarter Report


2009 Third Quarter Report


Second Quarter 2009


First Quarter 2009


Annual Report 2008


Third Quarter 2008


Second Quarter 2008

 

Adnet Communications Inc.